Suppose you have a big project plan with lots of tasks. You would only like to display incomplete tasks in a Gantt view. What should you do?
‘Filter’ is the answer to this question. Filter specifies which task or resource information should be displayed or highlighted in a view.
Select one of the following:
Select Incomplete Tasks from the drop down menu in Filter on the Formatting Toolbar
- Or, from the Menu, select Project\Filtered For: All Tasks\Incomplete Tasks
Only Incomplete Tasks will be displayed. If Incomplete Tasks are still displayed then follow these steps:
- Navigate to View\More Views.
- From the dialog box, select Gantt Chart and click Edit.
- Uncheck the Highlight filter and click OK.
This will ensure that only Incomplete Tasks are displayed.