Microsoft Project Tips – How to Hide Completed Tasks in Gantt View

Suppose you have a big project plan with lots of tasks. You would only like to display incomplete tasks in a Gantt view. What should you do?

 

‘Filter’ is the answer to this question. Filter specifies which task or resource information should be displayed or highlighted in a view.

 

Select one of the following:

  • Microsoft Project 2007 Filter ToolbarSelect Incomplete Tasks from the drop down menu in Filter on the Formatting Toolbar  

 

 

  • Or, from the Menu, select Project\Filtered For: All Tasks\Incomplete Tasks

 

Only Incomplete Tasks will be displayed. If Incomplete Tasks are still displayed then follow these steps:

  1. Navigate to View\More Views.
  2. From the dialog box, select Gantt Chart and click Edit.
  3. Uncheck the Highlight filter and click OK.

 

This will ensure that only Incomplete Tasks are displayed.