Sometimes you may want to mark major event in a project, for example indicate the beginning and end of the project or display the end of a major phase. You can use milestones to do that. To create a milestone follow the steps:
- In Gantt Chart View, in the Task Name column, type the name of a milestone
- In the Duration column type 0 and press ENTER
In the Gantt Chart the task will be displayed as a black diamond symbol ♦.
Want more tips? Click on Microsoft Project Tips and Tricks